Earned Value Management — simple & clear
Aligned definitions. Interpreting signals. One EAC only: EAC = BAC / CPI.
Key Definitions (short, aligned)
PV
Planned ValueBudget for work scheduled to be done.
EV
Earned ValueBudgeted value of work actually done.
AC
Actual CostWhat you paid for work performed.
BAC
Budget at CompletionTotal approved budget.
Healthy
CPI ≥ 1 • SPI ≥ 1
Unhealthy
CV < 0 (overrun) • SV < 0 (behind)
Micro example — read the signals
- Given: EV=240k, AC=300k, PV=260k, BAC=900k
- Compute: CPI=0.80, SPI≈0.92, CV=−60k, SV=−20k
- Interpret: over budget & behind schedule.
- Forecast (trend): EAC=BAC/CPI=1,125k → VAC=−225k
Formulas — one per line (no confusion)
We only use EAC = BAC / CPI for forecasting.
- CV = EV − ACCost variance
- SV = EV − PVSchedule variance
- CPI = EV ÷ ACCost efficiency
- SPI = EV ÷ PVSchedule efficiency
- EAC = BAC ÷ CPITrend (only one used)
- ETC = EAC − ACTo finish
- VAC = BAC − EACAt completion variance
- TCPI(BAC) = (BAC − EV) ÷ (BAC − AC)Target to hit BAC
- TCPI(EAC) = (BAC − EV) ÷ (EAC − AC)Target to hit EAC
Mini Example — Variances
- Inputs: EV=400k, AC=470k, PV=420k
- CV=−70k; SV=−20k → overrun & behind
Mini Example — Indices
- Inputs: EV=600k, AC=500k, PV=640k
- CPI=1.20 (good); SPI=0.94 (slightly behind)
Mini Example — EAC (trend)
- Inputs: BAC=1,000k; EV=350k; AC=420k
- CPI=0.8333 → EAC=1,200k; ETC=780k; VAC=−200k
Worked Examples — step by step
Case 1 — Interpreting Indicators
- Given: EV=240k, AC=300k, PV=260k, BAC=900k
- CPI=0.80; SPI=0.92
- CV=−60k; SV=−20k
- EAC=900/0.80=1,125k; ETC=825k; VAC=−225k
Case 2 — Healthy CPI, slower SPI
- Given: EV=600k, AC=500k, PV=650k, BAC=1,400k
- CPI=1.20 (good); SPI=0.92
- EAC=1,166.7k → VAC≈+233k
Case 3 — Mid-project check
- Given: EV=380k, AC=460k, PV=420k, BAC=1,050k
- CPI=0.826; SPI=0.905
- EAC≈1,272k; ETC≈812k; VAC≈−222k
Case 4 — Strong recovery
- Given: EV=750k, AC=680k, PV=700k, BAC=1,500k
- CPI=1.103; SPI=1.071
- EAC≈1,360k → VAC≈+140k
Calculators
Variance & Indices
EAC (trend only)
Practice Quiz
Exam Mode
Question palette
Score meter
0%
Glossary
Exam Tips
- Use only EAC = BAC / CPI.
- State the sign: CV negative = overrun; SV negative = behind.
- Workflow: CPI → EAC → ETC → VAC.